Bulgaria has offered to Rosatom to participate in the construction of Unit 7 of Bulgaria's Kozloduy Nuclear Power Plant, NPP.
The news was announced by the Deputy CEO of Rosatom, Kiril Komarov, speaking at the international "Atom Expo 2012" forum, and cited by Russia's RIA-Novosti and the Bulgarian Standard daily.
"The Bulgarian side proposed to examine our inclusion in the construction of Unit 7 of Kozloduy NPP. I believe that despite Bulgaria abandoning the Belene NPP project, our partnership continues and has good prospects," said he.
When the center-right Citizens for European Development of Bulgaria party GERB government suspended the Belene NPP project, it was decided that one of the reactors earmarked for it would be used as unit 7 at the Kozloduy NPP.
After almost three years of balking at it, the Cabinet of Prime Minister, Boyko Borisov, abandoned the NPP project in March 2012. The plant was supposed to be built by the Russian company Atomstroyexport, a subsidiary of Rosatom.
The construction of the Nuclear Power Plant in the Danube town of Belene would have cost EUR 10.35 B in the best case scenario, according to the estimates of Bulgarian government's consultant for the project, the HSBC bank.
The 2006 contract that Bulgaria's Socialist-led Three-Party Coalition Cabinet signed with Atomstroyexport for the construction of the Belene NPP was for EUR 3.997 B. Subsequently, however, it became clear that the final price would be higher, which led to years of haggling and seeking of "strategic investors" by the Bulgarian government of Borisov.
At one point Rosatom put the price of the construction of the 2000 MW plant at EUR 6.3 B, while Bulgaria insisted on EUR 5 B. The Borisov Cabinet terminated the project regardless of the Russian compensation claims, arguing that it was "economically unfeasible" for Bulgaria.
Bulgaria's government also recently decided to start the construction of a new reactor in Kozloduy after it gave up on the construction of Belene. Thus, the Bulgarian government decided to install in Kozloduy the 1000 MW reactor that the Russian state company Atomstroyexport already produced for the Belene NPP.
Αρχική δημοσίευση από Novinite.
Οικονομία
Το Ταμείο αύξησε την πρόβλεψή του για τον πληθωρισμό στο 4,9% και πλέον αναμένει έλλειμμα τρεχουσών συναλλαγών 8% του ΑΕΠ.
Βοηθός του InvestBulgaria
Οδηγοί, περιοχές και εταιρείες για τα σχέδιά σας στη Βουλγαρία
Τι θέλετε να κάνετε σήμερα στη Βουλγαρία;
Οι απαντήσεις γράφονται από τεχνητή νοημοσύνη και μπορεί να περιέχουν λάθη: ελέγξτε τις σελίδες που προτείνονται. Μην εισάγετε προσωπικά στοιχεία.