Bulgaria has approved a €110 million Just Transition Fund grant call for small and medium-sized firms in Stara Zagora, Pernik and Kyustendil, after a €178 million call was cancelled following an audit. Selection is set to rely more on measurable financial indicators, and applications are expected to open by the end of the year.
What happened
On 20 November the monitoring committee of Bulgaria's Regions in Growth Programme 2021-2027 approved a new €110 million grant scheme for micro, small and medium-sized enterprises in the coal regions of Stara Zagora, Pernik and Kyustendil, BTA reports. The money comes from the EU's Just Transition Fund. Companies in ten neighbouring municipalities, including Sliven, Yambol, Haskovo and Dimitrovgrad, are also eligible. Deputy Regional Development Minister Desislava Georgieva said the ministry expects to open the call for applications by the end of the year.
Stara Zagora region and the adjacent municipalities receive the largest share, €80.2 million, with €17.3 million for Kyustendil region and €12.5 million for Pernik region. Grants will range from €50,000 to €300,000 per project for micro and small enterprises and up to €500,000 for medium-sized ones. They can pay for machinery and equipment, specialised software, construction and installation works, and staff training and retraining. The ministry expects at least 180 enterprises to receive support and more than 250 new jobs to be created.
The figures and background
The scheme is a second attempt. In January 2025 the ministry opened a call titled Diversification and adaptation of SMEs to the economic transition, with a budget of 250 million leva (€178 million), and more than 2,100 project proposals had been submitted by May 2025, Economic.bg reports. An extraordinary audit, launched after complaints, confirmed a flawed organisation of the evaluation process, subjectivity, a lack of transparency and unequal treatment of applicants, the ministry said in July. In June 2026 Regional Development Minister Ivan Shishkov announced disciplinary proceedings against officials and evaluators, and a month later the call was terminated.
The new budget is smaller than the cancelled one, and its regional split changed between the draft and the approved version. In October Kyustendil was due to receive just over €10.2 million; the approved figure is €17.3 million. The Stara Zagora share was cut from about €86 million to €80.2 million and the Pernik share from €13.6 million to €12.5 million, according to Economic.bg.
The call is part of a larger envelope. The European Commission approved about €1.2 billion from the Just Transition Fund for Bulgaria in December 2023, together with territorial plans for the three regions. It said at the time that the money should create jobs and reskilling opportunities for more than 15,000 workers and rehabilitate 2,190 hectares of land. Stara Zagora hosts coal mines and four thermal power plants, while in Kyustendil the phase-out of coal began two decades ago, the Commission noted. By 5 November 2026, €1.386 billion, or 98.5% of the budget of the programme's Just Transition priority, had been contracted through 11 calls and 454 contracts, the ministry said.
Payments are slower than contracting. Across the whole Regions in Growth Programme, contracts exceed €3 billion, or 92.5% of the budget, but payments to beneficiaries amount to €826 million, or 25%, BTA reports.
How Bulgaria compares
Commission figures put Bulgaria's Just Transition Fund allocation at €1.198 billion, or €1.474 billion including national co-financing. That is less than Romania's €2.14 billion and Greece's €1.375 billion, but far more than Croatia's €186 million, Hungary's €261 million or Slovenia's €259 million. The EU total is €19.68 billion.
What it means for investors and companies
For manufacturers and service companies in the eligible areas, the call offers non-repayable capital grants on a scale suited to equipment upgrades rather than large greenfield projects: a medium-sized company can receive at most €500,000.
The selection rules are set to differ from the cancelled call. In July the ministry said the new model would use criteria calculated automatically in its UMIS information system from objective indicators such as EBITDA and financial profitability, require existing companies to have been registered for at least three years, and publish exhaustive lists of eligible and ineligible activities linked to the National Strategy for SMEs 2021-2030. Criteria based on business plans and market forecasts, which the ministry called a major source of subjectivity, are to be dropped. The draft methodology published in October also gave more weight to measurable financial indicators, Economic.bg reports. Cutting the grant intensity under de minimis rules to 65%, so that more companies can be supported, was discussed in July, and Deputy Prime Minister Atanas Pekanov said applicants should make their own contribution.
Such rules would favour established, profitable companies with solid financial statements over start-ups or firms with weak recent results. Businesses with operations in the region will need to check whether their activity is on the eligible list. The 2025 call attracted more than 2,100 bids for a larger budget, which suggests strong competition, and companies that applied then will have to apply again under the new terms.
Grants are not the only route. The ministry says €600 million in financial instruments combining loans and grants will be offered under the same Just Transition priority, following an agreement signed in September 2026 with the Fund Manager of Financial Instruments in Bulgaria. The main risk is time: the ministry said faster implementation had prevented a loss of Just Transition money in 2026, but a call that opens in late 2026 leaves companies less time to buy, install and report on equipment.
What to watch next
The call is expected to open by the end of December 2026. The key details to watch are the final guidelines: the aid intensity, the list of eligible activities, the scoring formula and the length of the application window. Also worth following are a separate €30 million call for a field centre for defence and dual-use technologies in the Stara Zagora area, planned before the end of the year, the launch of the €600 million in financial instruments, and whether payments under the programme pick up from the current 25% of the budget.